Louisiana · La. R.S. 9:4801 (Private Works Act)
Lien Clock runs.
Statement of claim — 60 days after termination / completion

Louisiana’s Private Works Act is a privilege system with no 20-day preliminary notice. File the statement of claim within 60 days after a notice of termination is filed, or after substantial completion if none is filed (R.S. 9:4822). We serve the owner and surety and calendar that filing.
Start the clock · We draft. You approve. We send.
Statutes last checked: November 16, 2026 (Lien Clock citation, La. R.S. 9:4801 (Private Works Act), against the state’s statute text). Not legal advice.