Georgia · O.C.G.A. §44-14-361.5 / §44-14-361.1
Lien Clock runs.
Notice to contractor 30 days (if NOC filed) · lien 90 days

If a notice of commencement is filed, subs and suppliers who did not contract with the prime must send the prime a notice to contractor within 30 days after the later of the filing or their first delivery (§44-14-361.5). The claim of lien is filed within 90 days after completion of the work (§44-14-361.1). We serve that notice and calendar the 90-day claim window.
Start the clock · We draft. You approve. We send.
Statutes last checked: November 16, 2026 (Lien Clock citation, O.C.G.A. §44-14-361.5 / §44-14-361.1, against the state’s statute text). Not legal advice.